Thursday, 9 July 2015

Poor Workmanship in Housing Construction 

(3)

You thought that you are designing the column base as "fixed", then you found the actual situation at site was far from your ideal assumption. What would happen to the structural performance when completed even after you had repaired? 
What caused this defect?  


If you look at the photograph closely, you will see the aggregates segregating at the base and the aggregate sizes are irregular. These aggregates are un-sieved river gravels, with some exceeding 50mm. 
The steel bars are not vertical and evenly distributed, in fact forcefully bent here and there. The starter bars from below the ground beams are not aligned with column bars above the ground floor.

So you can see many basic problems from this construction:

(a) Setting up. The survey or measurement was not done properly, therefore the vertical bars were not installed at the exact locations. (In fact, after putting up the brick wall, the rooms were found to be not rectangular or squarish),

(b) Formwork. If the formwork was not tight, leaking of cement grout could cause honeycombs,

(c) Concrete mix. Concrete was one of the most uncertain material when ready-mix was not available. Site mix was so variable that until you tested it, you wouldn't know the result. 
(Concrete is made up of cement, fine aggregates, coarse aggregates and water. The designer often specifies Grade 20, 25 or 30 for the structures, while lean concrete uses Grade 15. Grade 20 means that the concrete will achieve at least 20N/sq.mm compressive strength in 28 days. In the past, the concrete was specified with 1:2:4, 1:1.5:3 or 1:1:2 mix to achieve Grade 20, 25 or 30 respectively. 1:2:4 means one part of cement, 2 parts of fine aggregates and 4 parts of coarse aggregates. 
Is the cement fresh or properly stored? Cement deteriorates fast if it is not properly stored. 
Then the aggregates are another big uncertainties. Are they from quarries, blasted and manufactured from igneous or metamorphosed or limestone rocks? Generally, these quarry-made aggregates are more uniform and well controlled, but thiswhich also depends on quality of machineries and management control. 
But if the aggregates are river gravels, are there proper sieving procedures to obtain required sizes and cleaning to remove all the dirts, sticky silt and clay? The same applies to the fine aggregates, quarry made or river sands? Fine aggregates have generally four different zones, which zone of the fine aggregates at your site belongs to?
In buildings, the coarse aggregates specified should not exceed 20mm generally, it appeared that this construction did not comply based on the larger aggregates dug out at the problem area. When large gravels are used, they would stopped by the stirrups used as perimeter bars, then concrete would not be able to flow down to the bottom.
Finally, how much water should be added to the mix ? Water-cement ratio of 0.45 is an idealistic proportion, it will give best strength, but it is too dry for concreting work in small column. Therefore, you may need to go to 0.6 for ease of compaction and construction. Often, admixture is added to improve the workability (high slump) without sacrificing the strength. But admixture is expensive. Thus it is easier by just putting in more cement and water to achieve the same slump.
To achieve the required strength and slump, trial mix must be done much earlier before any concrete mix and materials can be approved to use at the site. It appears this site had no such trial mix,

(d) Concreting. Concrete is time dependent, the longer you wait the more difficult to work. Concrete must be poured, the best within half an hour after the mix and probably within one hour by adding chemical admixture . The moment it is hardened, it will difficult to put into place even with internal vibrators. Engine-run internal vibrators must be used to ensure that the concrete is properly compacted with no gap and holes. Otherwise, honeycombs will appear. But avoid over-compaction because it will lead to segregation of coarse aggregates at the bottom. Sometimes, you will see the workers pouring water into the concrete when they find the concrete is dry and this in fact reduce the concrete strength drastically with a higher water-cement ratio. Concrete cubes made from concrete before adding water does not reflect the actual concrete quality.

(e)  Supervision. The supervision team really has to improve the skill. Unfortunately, this supervision team who was not competent enough to do the work, was sent by the client. The Designer has to keep on reminding and writing instructions to such team,

(f)  Design has to be conservative when facing poor Contractor, incompetent supervision team and indifferent Client. Also avoid using too small columns, often requested by Architect, even though they might slander you by branding you lousy engineer if you didi not comply. The final liability is still with the Engineer.  Now the new Eurocode requires at least 200mm width for structures to reduce this kind of concreting problem.

Below is another photograph also showing slender column, probably large aggregates, conjested steel reinforcements, insufficient compaction, causing holes and honeycombs.



Tuesday, 7 July 2015

Poor Workmanship in Housing Construction 

(2)

Yes, just fill up, flatten the muddy soil within the ground beams, pour the concrete over it, the ground floor slab would be finished. Everything would buried under the feet. Only the new concrete surface would be seen and admired by the people!
What about the floor that sink and crack before and after being hardened?
Never mind, claim progress and money first and think about the problems later.


Often, the local Contractors are incompetent and ignorant, they cannot read Contract Specification (in English), but they can tell you that they have constructed buildings for more than twenty years. Therefore, they do not need the young Designers or Resident engineers to tell them what to do.

To prevent such situations, Site Engineers have to study what the Contractors/workers are doing at site, foresee coming problems and advise them immediately to take precautionary steps firmly when the machineries are around. For example, drainage is one of the most important temporary works in view of the frequent raining. By just building an earth drain surrounding the site and discharge to appropriate outlet will help to keep the site dry. Pumps must be available if water cannot be discharged speedily. Excavated earth shall be transported away as soon as possible if it is not required further. Outside ground level shall be lower than the designed floor level. Earthwork cannot be done on wet days, you cannot compact wet clayey soils! Sand is a better material for working in the wet season. The site Engineers have to be knowledgeable in the Specification and firm in authority before they are able to instruct the "experienced" contractors in writing, if they are not following orders.



Poor Workmanship in Housing Construction (1)

One look at this site, you already know the poor site management of the Contractor. 
Drainage was not provided, soils were littered everywhere and after raining, the slurry invaded the half finished ground floor. 
Do not expect the Contractor to clean the unfinished structures, the Contractor just continued pouring the new concrete over the soiled surfaces. What was the supervision team doing? 
No or poor supervision, many developers were not willing to spend money on supervision which also slowed down the construction. Many Contractors also cited low contract price and others were just poor in management and knowledge.
Good luck buyer, if you happen to buy one such property!






Burnt Umber/Bergundy Rock Fragment in River Gravels

This half-baked shades of brown coloured stone with distinct layers was found among the river gravels. Obviously, it had been subjected to high pressure and temperature, such that part of the fragment was fused to form very hard surface. Certainly durable, even after soaking in the water, rubbed against other gravels and rolled in the river bed for thousands of years, it still could survive. 
But if you break it apart, you will find the un-fused part of Shale and some stone fragments, which have low strengths.
That is why, if the river gravels are not screened and unsuitable materials removed, there will be localised weak spots in the concrete structure and is especially dangerous in slender columns.

Anyway, it is a beautiful natural product, but why Bergundy colour?


Various Shapes of River Gravels

They rolled tens of miles, some perhaps hundreds from the mountainous interiors to the flat plains through the help of rain, heat and water flows. Many had lived thousands of years, scoured from the bedrocks to become boulders, cobbles, and then gravels. The bedrocks in Sarawak are generally sedimentary in nature, which are easier to erode but the metamorphosed action and volcanic intrusion help to harden the rock which laid the basis for forming these hard gravels. Graywacke, sandstone, slate, phyllite, quartzite, limestone, etc. are common gravelly materials. There are many shapes and sizes too, round, oval, triangular, squarish,irregular, you name it, but most of them are smoothened and rounded at the corners. They are beautiful creatures formed by Nature.



Thirty years ago, these gravels were used for construction of concrete structures, especially in Sibu, where there was no igneous rock quarry but plentiful supply of river gravels. Concrete strengths were seldom expected to be more than Grade 30 (30 N per sq.mm). Actually, Grade 20 was most of the time adopted for design. Low strengths were due to the unpredictable strengths of gravels and often stained with a lot of silty materials. In fact, I also used the crushed boulders for some of the bridge foundation blocks in the Sarawak interiors. More cement was often required for such concrete.

Today, I collected these materials for landscaping.

Sarikei High School Classroom Block Exrension

During 1987, the Principal of the School asked me to assist designing a 2-storey extension block at the foothill of the small hill, which was the site of the old library. The new block would have six classrooms.
Being old student, it was my moral duty to help for providing me education. 
Some excavation of soil was required to bring to the same level of the old block. This excavation varies from 0m to 2m. Was piling necessary for the foundation? This would require higher cost which the School was lacked of. Of course, the safety of the students was my main concern.
A simple Soil Investigation using Mackintosh Probe Tests were carried out. It revealed shallow firm to stiff residual soils up to 4m depth across the building with some variations. A bearing capacity of 150KN per sq. meter could be used at 1.0 m below the intended ground level. Spread footings or strip footings were all viable. The recommended footing location was 1.5m below ground level to reduce the effect of water level fluctuations.
Normally, the ground floor has ground beams tie to the columns and these beams were 230 wide x 600-750mm depth, with 300mm column stumps above the footings.

I decided to use the strip footings by providing 200-300mm thick base slab combined with 750mm ground beams longitudinally thus having inverted T-shape Footings with a total depth of 1050mm below designed ground level. This would help to stiffen the structure to distribute some variations of soils and fluctuation of water levels, at the same time cut down the reinforcements of the ground beams and foundation. Shallower foundation also meaned easier construction.

Cantilever beams and expansion joints were provided to join to the old blocks. It was expected there would be a little movement between the old and new block.

The extension building was completed in 1989 and worked well in accordance to the design intention at the minimum cost.



The strip footing looks like this picture from another project, but was not flooded.



Microtonalite Stone aggregates from Quarry

Stone aggregates from quarries for making concrete are quite easily available in Kuching. They are either crushed from Igneous rocks Microtonalite, Granite, Basalt, Andesite or from sedimentary rock Limestone. Igneous rock has the best quality while Limestone is moderately good for concrete usage, but not recommended for foundation structures (acidic ground water) and structures which expose to acid such as roof slabs (acid rain).
This photo shows the commonly available Microtonalite stone aggregates from Kuching.


Central and Northern Sarawak regions such as in Sibu, Sarikei, Bintulu and Miri, do not have igneous rock quarry because of the unfavourable Geology. The stone aggregates used are therefore either the river gravels or the metamorphosed/cemented Sandstone and Limestone Quarries, which are of inferior quality compared to igneous rock quarries. Therefore, if good quality stone aggregates are to be used, they have to be bought from Kuching, which are expensive due to distance.
To determine whether the aggregates are of good quality, there are many tests to be done. These include Uni-axial compression tests for parent rocks, Sieve analysis, Crushing Value test, Impact Value test, Los Angeles Abrasion test, 10% fines test, Specific gravity, water adsorption test and sodium sulphate test, just to name a few major ones. In view of the cost and fear of failing, not many quarries or suppliers are willing to do such tests. But the local Authorities require Building structures to comply to the MS/BS standards, Engineers have to check the quality of the stone aggregates before being allowed to use. But how many of them really checked these requirements, especially the Central and Northern Regions where tests are not even available?